Zenith

High noon for Chiyaba: the phase that takes the site to its full 100 MW.

The second 56 MWac phase on the Chiyaba site, taking the plant to its full 100 MWac licence once the dedicated evacuation infrastructure is commissioned.

56MWacexport capacity
79MWp DCinstalled, single-axis tracking
Funder discussionsAdvanced development · in funder discussions
ChiyabaChiyaba, Kafue District, Lusaka Province

How Chiyaba connects.

Chiyaba will connect to the ZESCO 88 kV network at Gota Gota substation through dedicated evacuation infrastructure funded by Mpishi Energy under the Implementation Agreement, replacing the originally planned connection at 11 kV with a step-up to 88 kV. One fewer transformation stage, a direct route onto the transmission network, and a single connection point shared by Daybreak and Zenith.

Originally planned
  1. Solar + storage
  2. 11 kV connection
  3. Step-up to 88 kV
  4. Grid
Now
  1. Solar + storage
  2. Plant substation
  3. Direct 88 kV line
  4. Gota Gota
Connection voltage
88 kV
Grid substation
Gota Gota (ZESCO)
Phase 1 export
44 MWac
Full site
100 MWac after upgrade

Schematic, not to scale. Connection terms per the ZESCO Grid Connection Agreement and grid studies in the data room.

The project

Zenith shares Daybreak's land, licence, grid studies and environmental authorisation, which allows it to advance at a fraction of the usual cost and time. It shares the same 88 kV connection at Gota Gota substation, and energisation is sequenced behind the substation upgrade through a phased export commissioning condition agreed with the regulator. This structure preserves the full 100 MWac licence while keeping Phase 1 construction on its own critical path.

Status and approvals

  • LicenceWithin the 100 MWac Chiyaba generation licence
  • Environmental authorisation (ZEMA)Covered by site ESIA
  • Grid studiesCompleted with ZESCO for full 100 MWac
  • Export conditionPhased export commissioning · regulator engaged
  • Evacuation infrastructureGota Gota substation upgrade · scoped, costed, contracted · Mpishi-funded
  • Land tenureFreehold title · registered
  • OfftakeSame PPA framework · heads of terms agreed · premium offtaker

Key figures

  • Combined site output≈ 182.5 GWh / yr P50 (PVsyst, Solargis data)
  • Grant supportEvacuation infrastructure grant in final review
  • Storage20 MW / 40 MWh LFP, 2-hour (co-located) · shared BESS control architecture
  • Project companyZenith Chiyaba Limited

Figures are indicative and subject to the financial model and technical reports in the data room. Generation and emissions estimates are set out in the technical reports in the data room.